摘要
以成都地铁六号线一、二期工程为例,介绍地理位置及地质条件信息,具体从盾构施工技术的主要方法上对测量环节所造成的误差加以详细的分析与说明,分析测量基本内容与作用结合测量要求,提出质量控制措施,可为其他类似的工程提供经验与借鉴。
Taking the first and second phases of Chengdu Metro Line 6 as an example,the geographical location and geological conditions information will be introduced.The errors caused by the measurement links will be analyzed and explained in detail from the main methods of shield construction technology.Combining the measurement requirements with the function and proposing quality control measures can provide experience and reference for other similar projects.
出处
《建筑技术开发》
2018年第22期50-51,共2页
Building Technology Development
关键词
地铁隧道
盾构施工
测量误差的控制
贯通
subway tunnel
shield construction
measurement error control
penetration