摘要
兰州市中央大道提升改造建设项目施工期间的交通导改方案按照"纵向段落划分、横向施工顺序划分、交叉口施工顺序划分"进行交通组织,在施工期间做到了道路和交叉口交通不中断,对沿线街坊、单位及居民出行影响较小,保证了项目按时完成。
During the construction of Lanzhou Central Avenue Upgrading and Reconstruction Project, the traffic guidance scheme is organized according to the "vertical section division, horizontal construction sequence division and intersection construction sequence division". During the construction, the traffic of roads and intersections is uninterrupted, which has little impact on the travel of neighborhoods, units and residents along the line, and ensures the project to be completed on time.
出处
《城市道桥与防洪》
2019年第2期139-142,M0016,共5页
Urban Roads Bridges & Flood Control
关键词
主干路
交通导改
断面划分
施工顺序
trunk road
traffic guidance
section division
construction sequence