摘要
以寺河矿常店进、回风立井与井下东六盘区大巷贯通为例,通过对测量方案及其允许误差确定,在地面采用D级DPS控制测量,井下采用全站仪导线测量和陀螺全站仪定向测量,减收了工作量,缩短了工作时间,大大提高了两井贯通的精度,为今后的大型贯通提供可靠的技术参考。
Taking the return air shaft and the main roadway of Dongliupan underground as an example,through the determination of the measurement scheme and its allowable error,the D grade DPS control survey is adopted on the ground.The downhole use of total station traverse survey and gyroscope total station orientation survey reduces the workload,shortens the working time,greatly improves the precision of the two wells through,and provides a reliable technical reference for the large-scale penetration in the future.
作者
齐跃波
Qi Yuebo(Sihe Mine of Jincheng Coal Mine Group,Jincheng Shanxi 048205)
出处
《机械管理开发》
2019年第1期225-227,共3页
Mechanical Management and Development
关键词
贯通测量
GPS
控制测量
限差要求
误差预计
精度评定
through measurement
GPS
control measurement
error limit requirement
error prediction
accuracy evaluation