双代号网络图在地籍调查项目进度控制中的应用 被引量:1

Application of Double Code Network Diagram in Progress Control of Cadastral Investigation Project
下载PDF
导出
摘要 本文以某市村庄地籍调查项目为例,在明确各工序之间的衔接关系的基础上,通过绘制双代号网络图,进行相关时间参数计算,确定关键路径及相应的关键工作,同时计算出非关键工作的机动时间,为项目管理者合理安排项目进度、动态控制项目进度及资源配置提供依据。 This paper takes a village cadastral survey project in a city as an example to clarify the connection relationship between various processes.By drawing a double-code network diagram,the relevant time parameters are calculated,the critical path and corresponding key work are determined,and maneuver time for non-critical work is calculated,all of which provide a basis for the project manager to reasonably arrange the project schedule and dynamically control the project schedule and resource allocation.
作者 李颖捷 王高新 张愿 刘新宇 LI Ying-jie;WANG Gao-xin;ZHANG Yuan;LIU Xin-yu(Nanjing Institute of Surveying,Mapping and Geotechnical Investigation,Corp.Ltd,Nanjing Jiangsu 210019,China;Shuyang City Land and Resources Bureau,Shuyang Jiangsu 223800,China)
出处 《现代测绘》 2018年第6期62-64,共3页 Modern Surveying and Mapping
关键词 双代号网络图 关键路径 时间参数 double code network diagram critical path time parameter
  • 相关文献

参考文献2

二级参考文献4

共引文献1

同被引文献6

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部