钢管拱吊装施工控制研究 被引量:2

Study on Construction Control of Steel Tubular Arch Hoisting
下载PDF
导出
摘要 秭归青干河大桥主桥系跨度 2 5 6 .0 m中承式钢管砼桁架无铰拱桥 ,钢管拱吊装采用缆索吊机斜拉扣挂悬臂拼装法施工。通过工程实例 ,介绍秭归青干河大桥钢管拱吊装施工独特的施工方案与新型的施工控制方法及接头辅助临时连接、整体节段同时一次焊接合龙等施工新技术的应用及探讨。 Qinggan River bridge in Zigui is a CFST arch half through bridge with a main span of 256.0 m, the steel tubular arch was fastened and connected by cableway crane with cable stayed cantilever. Based on the case, this paper introduces the particular construction schema and new construction control method of suspending placement of the steel tubular. It also introduces some new construction technologies such as the temporary connection of adapters and the closing up of the whole articulations through welding.
出处 《武汉理工大学学报》 CAS CSCD 2002年第4期78-80,共3页 Journal of Wuhan University of Technology
关键词 钢筋拱 施工控制 临时连接 整体合龙 吊装 秭归青干河大桥 steel tubular arch construction control temporary connection closing up of the whole structure
  • 相关文献

参考文献1

  • 1陈宝春.钢管砼拱桥设计与施工[M].北京:人民交通出版社,1999..

共引文献2

同被引文献2

引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部