摘要
对于大跨度、高举架建筑 ,供暖系统的垂直失调是影响其供暖效果的重要原因 ,至今没有一种完善的解决方法。通过对北方航空公司沈阳机库供暖系统的改造 ,初步解决了原系统存在能耗大 ,而又难以满足供暖温度要求的问题。该改造工程设计简单、工期短 ,改造后系统运行管理简便。
In a large span and high architecture,vertical imbalance of heating system is a main reason for affecting the effectiveness of heating.Now there is no better solution to resolve the heating problem.By means of rebuilding the heating system of Shenyang aerooplane hangar,we can basically resolved the defects of the old system,such as overfull energy consumption and hower temperature.This rebuilding project have many merit,for example design is simple,time limit for a project is short,running and manage is easy and energy is sparing.
出处
《节能》
2002年第4期26-27,共2页
Energy Conservation