CCPP焦煤二次净化系统运行已有三年多,文章通过对脱萘、脱苯再生冷却塔再生过程中存在的问题,进行论证分析,为下一步再生冷却塔的优化改造提供可行性理论依据。
The coke secondary purification system of CCPP has been running more than three years. By analyzing and demonstrating the problem appeared in the regeneration process of regenerative cooling tower's naphthalene removal and benzene removal, this article can supply the feasible theoretical basis for the next staged optimal modification of regenerative cooling tower.
出处
《包钢科技》
2014年第3期34-35,61,共3页
Science & Technology of Baotou Steel
关键词
CCPP
净化系统
脱萘
脱苯
再生
CCPP
purification system
naphthalene removal
benzene removal