摘要
介绍了河津电厂进口机组锅炉设备的设计特点及调试过程 ,分析了调试阶段遇到的主要问题 。
The designing characteristics and commissioning process about imported boiler equipments in HeJing power plant were introduced and the main problems were analyzed in phase of commissioning.It can be regarded as a reference for the designing and commissioning of large type boiler in power plant.
出处
《山西电力》
2002年第1期48-50,57,共4页
Shanxi Electric Power