摘要
结合国产引进型 600 MW机组设计和试运过程中存在的问题,对汽水系统的低压给水再循环系统、发电机氢冷却器冷却水系统、闭(开)式循环冷却水系统等进行了优化,并对主厂房的布置提出了优化建议,可供工程设计参考。
Aimed at the problems in design and commissioning of home introduced unit of 600 MW,the optimizationis set up for low-pressure feed-water system,cooling water system of hydrogen cooler and closed or open cyclecooling water system of steam/water system. The optimizing layout of main machine hall is submitted.
出处
《吉林电力》
2002年第2期5-8,共4页
Jilin Electric Power