通过北氵名河铁矿基建期间发生的签证工程 ,阐述了签证工程管理的重要性及其操作程序 ,从而总结出签证工程的方案审批、现场记录认证、费用计算、工期考核的办法 。
Through the certification engineering occuring during the capital construction period of Beiminghe Iron Mine,the importance and the operation sequences of the management of certification engineering are expounded and the methods of the examination and approval of treatment scheme,on site recording,certification cost calculation and construction period check for the certification engineering summarized.Measures for further perfecting the certification management are raised.
出处
《金属矿山》
CAS
北大核心
2002年第5期18-20,共3页
Metal Mine
关键词
签证工程
工程管理
基建矿山
审批
费用
工期考核
Certification construction,Engineering management,Mine under capital construction