茅坪溪堆石坝沥青混凝土心墙施工温度控制 被引量:2

Temperature Control over Asphaltic Concrete Core in Maopingxi Dam
下载PDF
导出
摘要 三峡茅坪溪防护大坝是采用沥青混凝土心墙防渗的土石坝,其坝顶高程为 185 m,坝顶宽 12 m,最大坝高104 m,土石方总填筑量近1200万m3。其中作为防渗主体的沥青混凝土心墙高93 m,心墙总防渗面积4.62万m2,沥青混凝土总方量为5.31万m3。沥青混凝土施工工艺与普通水泥混凝土不同,它采用热施工,在一定温度条件下进行拌和、摊铺、压实,需严格实行施工温度控制。 The Maopingxi earth & rock dam with an asphaltic concrete core has a maximum height of 104 m, with a dam crest width of 12 m at elevation of 185 m, a total earth and rock backfill of nearly 1 200 m3. The asphaltic core has a height of 93 m, with a total asphaltic concrete volume of 53 100 mf and a total impermeable area of 46 200 m2. The asphaltic concrete construction is different from that of the traditional concrete. A hot construction approach is employed for the former. The asphaltic concrete must be batched, spread and compacted under certain temperature condition.
出处 《中国三峡建设》 2002年第4期22-23,共2页 China Three Gorges Construction
关键词 沥青混凝土 心墙 温度控制 施工技术 茅坪溪堆石坝 asphaltic concrete core temperature control construction technology Maopingxi dam.
  • 相关文献

同被引文献8

引证文献2

二级引证文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部