万家寨水库运用对上下游河段防凌的影响 被引量:2

Effect of the Wanjiazhai Reservoir Operation on Ice Prevention Upstream and Downstream
下载PDF
导出
摘要 万家寨水库修建后 ,喇嘛湾大桥以下河段成为稳定封冻河段 ,封冻河段增长 86km。冰塞、冰坝险情增加 ,水位壅高 ,沿河企业、村庄受灾。万家寨水库运用对河曲河段及天桥电站的凌情影响 ,既有有利的方面 ,也有不利的方面 ,应掌握时机降低库水位 ,适当抬高移民搬迁线。 After completion of the Wanjiazhai dam, the reach below the Lamawan Bridge has become regularly iced one, which has become 86 km longer than before. It has become more vulnerable to the risks by ice jamming, ice damming and water level rising so suffering the enterprises and villages beside it. The operation of the Wanjiazhai Reservoir has favorable and unfavorable influences over the ice situations in Hequ reach and near the Tianqiao Hydropower station. Therefore, it is suggested that drawdown should be effected at right occasions, and the emigrating line should be raised.
出处 《人民黄河》 CAS 北大核心 2002年第3期34-35,共2页 Yellow River
基金 治黄专项 ( 99Z0 3)
关键词 万家寨水库 防凌 水库运用 冰坝 ice prevention upstream and downstream reach the Wanjiazhai Reservoir the Yellow River
  • 相关文献

同被引文献20

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部