摘要
通过对盾构法隧道施工事例的试验统计 ,分析了盾构隧道施工过程中影响隧道掘进效率的各种因素 ,找到了瓶颈作用及其影响 。
Based on test and statistic data of a practical shield tunnel project, authors analyze factors that can influence tunnel\|driving efficiency in construction of shield tunnel structures, and find the bottle\|neck effect and its influence. These results have great use value to improve work efficiency. In this article, authors just analyze those test data, and analysis results will be used in sequent theses to optimize traffic management of tunnel driving.
出处
《施工技术》
CAS
北大核心
2002年第6期4-6,共3页
Construction Technology
关键词
隧道工程
盾构法施工
“瓶颈”作用试验
tunnel engineering
shield tunnel construction
bottle\|neck effect
test and research