摘要
认为流水步距的定义应为相邻的两个施工班组相继投入施工的间隔时间 ,不包括组织间歇、技术间歇、搭接时间等时间间歇 .指出了计算全等节拍流水施工工期常用公式中的一些弊端 。
The flowline pace should be defined as the interval time which the neighbouring workgroup has spent in succession,excluding organizing interval,technical interval,joining interval,etc.The disadvantages of the building date of calculating in congruence metre are pointed out and illustration of personal view is added.
出处
《石家庄职业技术学院学报》
2002年第2期22-23,50,共3页
Journal of Shijiazhuang College of Applied Technology