摘要
介绍了 1 2 0 0 / 1 2 5t桥式起重机的焊接工艺、生产制造及相关的质量保证措施 ,该起重机成功地应用于起吊三峡水电站 70
This paper introduced the welding process and manufacture and correlative quality assurance of 1 200/125 t over-head crane. 1 200/125 t over-head crane was applied to suspend the huge 700MW rotor of SANXIA water power station.
出处
《焊接》
2002年第7期26-29,共4页
Welding & Joining
关键词
桥式起重机
结构件
主梁
welding process, crane, framework, girder