北京轻轨铁路八达岭高架桥预应力施工 ,通过在固定端采用挤压锚、选用新型灌浆设备、实施二次张拉等技术措施和实行严格的质量保证、安全管理措施 ,保证了工程质量。
In construction of the Badaling prestressed viaduct of Beijing light railway, engineers adopted some techniques such as mouthpiece pressing anchors on fixed ends, new style grouting equipment, double stretching and so on, and strict measures, including quality assurance and safety management, to ensure construction quality.
出处
《施工技术》
CAS
北大核心
2002年第7期3-4,9,共3页
Construction Technology
关键词
北京
轻轨铁路
高架桥
预应力施工
锚具
urban railway
light railway
viaduct
prestress