摘要
土桥水库土坝地质条件较为复杂 ,根据其孔隙率较高的情况 ,选择适宜的灌浆压力和适宜的灌浆浆液 ,保证了其良好的技术性能和施工性能 ,既可节省费用 ,又能提高施工效率取得满意的效果。
The engineering geology condition of the Tuqiao reservoir earth dam is very complex.On the basis of high pore rate,an appropriate grounting pressure and grounting liquid were chosen.It can ensure the technologicol function and construction function.It can not only reduce cost but also improve construction effeciency.The grouning construction quality is satisfactory.
出处
《河北理工学院学报》
2002年第2期118-120,127,共4页
Journal of Hebei Institute of Technology