摘要
主要结合H工程的地基基础设计工作,阐述了地基土酸性污染,原有碎石桩地基加固以及钻孔灌注桩等复杂地质条件下的地基基础设计思路和方法,并着重对地基酸性污染机理和处理方法进行了详细论述。
The paper introduces the design of foundation works under complicated geological conditions including acid pollution of foundation soil, existing foundation improvement by gravel pile and bored pile and particularly discusses the mechanism of acid pollution of foundation soil and its treatment according to the design experiences of 'H' Project.
出处
《地下工程与隧道》
2002年第2期25-30,共6页
Underground Engineering and Tunnels