提出了适用于 2 2 0kV变电站 2 2 0kV部分单母线分段、线路变压器组主接线的备用电源自投装置的功能逻辑要求 。
Demands on function and logic of device for automatic converting of spare power supply which is suitable for the 220 kV main connection of single bus-bar section and line-transformer set of 220 kV substation are offered、analysized and discussed.