摘要
针对思山岭铁矿近1500m的深井,采取分段设计,分别按照井深1100m为5m^3吊桶,井深1100-1500m为4m^3吊桶,来选择计算钢丝绳、卷筒、电机和提升机,在保证劳动生产率、生产能力和工期情况下,降低了建设成本。
This paper researched Sishanling design was taken in this project, steel wire, nearly 1 500 meters large iron ore ultra-deep, segmented drum, motor and hoist were selected and computed, respec tively, in accordance with the depth of 1 100 m of 5 m^3 bucket, depth 1 100 meters to 1 500 meters 4 m^3 b ucket, the construction Cost of the project was reduced under the in labor productivity and production capacity and task duration to ensure the case.
出处
《煤矿机械》
北大核心
2014年第7期17-19,共3页
Coal Mine Machinery
关键词
超大超深
分段设计
立井
提升机
extra large ultra-deep
segmented design
mine shaft
hoist