摘要
结合某沿海电厂实例,介绍了软土地基处理方案的选择方法,着重阐述了采用换填、沉管砂桩处理电厂桩间软弱土的原则和注意事项,为类似工程选择多种方案处理软土提供了参考。
Combining with coastal coal-fired power plant as an example,the paper introduces the soft soil foundation treatment scheme selection, and mainly describes replacing and immersed-tube sand pile processing soft soil principles and matters,which has provides some guidance for se-lecting various soft soil treatment schemes for similar engineering.
出处
《山西建筑》
2014年第22期63-64,共2页
Shanxi Architecture
关键词
换填
沉管砂桩
软土
钻孔灌注桩
replacement
immersed-tube sand pile
soft soil
bored pile