期刊文献+

水电工程石方开挖中人、材、机单价确定方法探讨 被引量:1

Discussion on determination method for unit prices of manpower,materials and machinery in earth- rock excavation of hydropower projects
下载PDF
导出
摘要 水电工程施工时实际发生的人、材、机单价,是施工基本直接费测算中的重要基础数据,但对于如何确定人、材、机单价,目前并无统一的方法。结合某水电工程石方开挖施工基本直接费测算工作实测,分析总结了人工单价、材料单价及机械台时费的确定原则和计算方法,重点阐述了人工工资的构成范围、支付方式及边界条件。相关经验可为类似工程造价预算提供参考。 The practical unit prices of manpower, material and machinery are important base data in the basic direct cost estimation of construction, but now there is no unified and exhaustive method for their determination. With the combination of the cost estimation of a hydropower project, the determination principle and calculation method of unit prices of manpower, materials and machinery are summarized and analyzed. This paper lays emphases on the composition, payment mode and boundary condition of salaries. The relevant experience can provide references for cost estimation of similar projects.
出处 《人民长江》 北大核心 2014年第14期53-55,共3页 Yangtze River
关键词 人、材 机单价 石方开挖 工程造价 水电工程 unit prices of manpower,materials and machinery earth-rock excavation construction price hydropower project
  • 相关文献

同被引文献5

引证文献1

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部