达钢3~#高炉空料线放残铁安全停炉生产实践 被引量:1

Production Practice of Release Remainder Iron and Blowing-down with Lowered Stock Line of No.3 Blast Furnace at Dazhou Iron &Steel Group
下载PDF
导出
摘要 3#高炉首次在达钢集团实施空料线到风口后放残铁工作,经过炼铁厂相关技术人员的精心操作和控制,空料线到风口后从残铁口放出残铁110余吨,达到了成功停炉目的。 No. 3 blast furnace has the first implementation of lowering the stockline to the vent to release the residual iron in Dagang's history. Through the careful operation and control of rele- vant technical staff of ironworks, 110 tons of residual iron was released when the stockline was lowering to the vent to reach the shutdown purposes.
出处 《四川冶金》 CAS 2014年第4期20-23,共4页 Sichuan Metallurgy
关键词 高炉 空料线 放残铁 停炉 生产实践 blast furnace lowered stock line release remainder iron blowing down production practice