西安铁路枢纽新丰镇—窑村扩能项目研究 被引量:2

Study on Xinfengzhen-Yaocun Capacity Expansion Project in Xi'an Railway Hub
下载PDF
导出
摘要 随着西安铁路枢纽内引入线路的不断增加及枢纽功能逐步完善,枢纽内局部地区可能会出现能力不匹配的情况。针对西安枢纽东端新丰镇—窑村能力不足的现状,结合西安铁路枢纽规划,提出2个比选方案。经过技术经济比选,最终确定采用增建货车二线方案。按照推荐方案实施,将实现点线能力配套,缓解运输供需矛盾。 Following with continuous increase of introducing lines into Xi'an railway hub and gradual improvement of the hub functions, partial area inside the hub may occur capacity mismatching. Targeting with the status of Xinfengzhen-Yaocun capacity deficient in east end of Xi'an railway hub, and combining with Xi'an railway hub plan, this paper puts forward 2 comparing schemes. Through comparing the technologies and economics of the,schemes, finally, the scheme of adding second line of freight car was determined to apply. Through applying the recommended scheme, the supporting of station-line capacity will be realized and transoort suoolv-demand contradiction will be released.
作者 王军
出处 《铁道运输与经济》 北大核心 2014年第8期53-58,共6页 Railway Transport and Economy
关键词 西安铁路枢纽 扩能 方案 Xi'an Railway Hub Capacity Expansion Scheme
  • 相关文献

参考文献4

二级参考文献4

  • 1刘澜;王琳;刘海旭.交通运输系统分析[M]成都:西南交通大学出版社,2008.
  • 2中华人民共和国铁道部.铁路机车运用管理规程[M]北京:中国铁道出版社,2000.
  • 3帅斌;霍娅敏.交通运输经济[M]成都:西南交通大学出版社,2007.
  • 4中华人民共和国铁道部.铁路运输调度规则[M]北京:中国铁道出版社,2008.

共引文献1

同被引文献7

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部