摘要
随着西安铁路枢纽内引入线路的不断增加及枢纽功能逐步完善,枢纽内局部地区可能会出现能力不匹配的情况。针对西安枢纽东端新丰镇—窑村能力不足的现状,结合西安铁路枢纽规划,提出2个比选方案。经过技术经济比选,最终确定采用增建货车二线方案。按照推荐方案实施,将实现点线能力配套,缓解运输供需矛盾。
Following with continuous increase of introducing lines into Xi'an railway hub and gradual improvement of the hub functions, partial area inside the hub may occur capacity mismatching. Targeting with the status of Xinfengzhen-Yaocun capacity deficient in east end of Xi'an railway hub, and combining with Xi'an railway hub plan, this paper puts forward 2 comparing schemes. Through comparing the technologies and economics of the,schemes, finally, the scheme of adding second line of freight car was determined to apply. Through applying the recommended scheme, the supporting of station-line capacity will be realized and transoort suoolv-demand contradiction will be released.
出处
《铁道运输与经济》
北大核心
2014年第8期53-58,共6页
Railway Transport and Economy
关键词
西安铁路枢纽
扩能
方案
Xi'an Railway Hub
Capacity Expansion
Scheme