摘要 唐公塔站为既有大准铁路上的中间站,目前满足5 000 t列车到发条件,为使该站具有将5 000 t列车组合成万吨列车发往大同方向的能力,研究具备万吨列车会让条件和不考虑万吨列车会让条件情况下的车站改扩建方案。经多方案综合比选,唐公塔站改扩建方案将使改造后的车站具备万吨列车会让及万吨列车分解组合功能。 Tanggongta Station is an intermediate station on existing Datong-Jungar railway, and could satisfy the arrival-departure conditions of 5 000 t trains. In order to make Tanggongta Station having capacity of combining the 5 000 t trains into 10 000 t train and delivering to the direction of Datong, the paper studies the station reconstruction program under the situation of having 10 000 t train passing condition and not considering the passing condition. Through comprehensive comparison on many programs, the Tanggongta Station reconstruction program will have the functions of 10 000 t train passing and 10 000 t train uncoupling & combining after the station reconstruction.
作者 张旭
出处 《铁道运输与经济》 北大核心 2014年第8期64-68,73,共6页 Railway Transport and Economy
关键词 大准线 唐公塔站 扩能改造 方案 Datong-Jungar Railway Tanggongta Station Capacity Expansion andReconstruction Program
  • 相关文献

参考文献7

  • 1铁道第三勘察设计院集团有限公司.神华新准、大准、准池开行2万吨扩能方案研究[R].天津:铁道第三勘察设计院集团有限公司,2012.
  • 2铁道第三勘察设计院集团有限公司.神华准能肖家沙墉煤炭集运站可行性研究[R].天津:铁道第三勘察设计院集团有限公司,2012.
  • 3铁道第四勘察设计院.铁路工程设计技术手册(站场及枢纽)[M].北京:中国铁道出版社,2004.
  • 4胡显永,张炳民.重载铁路组合分解技术作业站设计探讨[J].铁道货运,2013,31(9):13-18. 被引量:5
  • 5余君领.重载铁路到发线有效长的确定[J].中国水运,2007,8(5):103-104.
  • 6刘其斌,马桂贞.铁路车站及枢纽[M].北京:中国铁道出版社,2005,(2).
  • 7中华人民共和国铁道部.GB50091-2006铁路车站及枢纽设计规范[S].北京:中国铁道出版社,2006.