CPR1000核电厂乏燃料水池冷却问题分析 被引量:6

Analysis of Spent Fuel Pool Cooling Problems of CPR1000 NPP
原文传递
导出
摘要 针对改进型三环路压水堆(CPR1000)核电厂在某些工况下可能丧失对乏燃料水池冷却功能的情况,以岭东核电厂为例,分析CPR1000换料水池和乏燃料水池冷却和处理系统(PTR)的设计基准、系统功能及缺陷,并结合技术规范的要求,提出PTR的改进措施。分析表明,CPR1000核电厂乏燃料水池冷却问题的原因是PTR设计没有充分考虑冗余性。建议从提高PTR冷却回路换热能力和降低乏燃料水池完全失去冷却风险方面进行改进。 The spent fuel pool of the CPR1000 type nuclear power plant ( pressure water reactor ) may loses it's cooling function in some conditions. The author uses Ling Dong NPP as the example to analysis the design basis, system functions and defects of PTR, and gives some suggestions to improve the PTR with considering the requirements of technical specification. The results show that the spent fuel pool cooling problem is because that the designer does not consider the redundancy of the PTR completely. The author suggests to improve PTR cooling capacity and reduces the risk of losing cooling of spent fuel pool.
出处 《核动力工程》 EI CAS CSCD 北大核心 2014年第4期90-93,共4页 Nuclear Power Engineering
关键词 乏燃料水池 冷却设计 技术规范 运行管理 Spent fuel pool, Cooling design, Technical specification, Operational management
  • 相关文献

参考文献1

  • 1广东核电培训中心.900MW压水堆核电站系统与设备[M].北京:原子能出版社,2006.

共引文献7

同被引文献19

引证文献6

二级引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部