摘要
阐述了隧道地震勘探的基本工程原理和TSP203超前地质预报设备在某隧道突水超前预报中的应用,并通过对某隧道进口段桩号ZK64+918处的超前地质预报结果与实际工程掌子面开挖揭露情况的对比,证明TSP对该处的超前突水预报是准确的,值得在复杂地质条件下隧道工程实践中推广。
This paper expounds the basic engineering principle of tunnel seismic prospecting and TSP203 advance geological forecast equipment application in advance of a tunnel water inrush forecast. Through a tunnel entrance pile number ZK64 + 918 advance geological forecast result and the actual engineering constraints excavation revealed contrast,forward to prove the TSP of water inrush forecast is accurate,is worth popularization in the tunnel under complicated geological conditions of engineering practice.
出处
《山西建筑》
2014年第25期200-202,共3页
Shanxi Architecture
关键词
隧道工程
TSP超前地质预报
隧道突水
tunnel engineering
the TSP advance geological forecast
the tunnel water inrush