摘要
文章介绍了一种通过蓄冷技术解决在无动力环境下核电厂主控室制冷的方法,为核电厂在严重事故(全厂断电SBO)下主控室温度调节提供了一种解决方法。分析了当核电站发生严重事故(SBO)状况下,为保证主控室操作员及重要设备安全采用的冰蓄冷控温系统的设计、自启动、运行方式。重点说明了该蓄冷方案的流程、换热计算方法,初步论证了该方案的可行性。
The paper described a method which used a passive ice-storage technical to cooling main control room air temperature, when nuclear power plant station black out (SBO). The paper analyzed the ice storage system design, start-up and operation when nuclear power plant at station black out severe accident. Through describing the ice-storage system process and heat transfer calculation method, generally proved the feasibility of the ice-storage system used for main control room.
出处
《广东化工》
CAS
2014年第15期58-59,共2页
Guangdong Chemical Industry
关键词
核电厂
主控室
可居留性
冰蓄冷
nuclearpowerplant
main control room
habitability
ice-storage