钢桁架和满堂红扣件式钢管脚手架联合支撑方案在溢洪道交通桥的应用 被引量:2

Application of Component Formworks-supporting Scheme Including Steel Truss Support Structure and Fastener Steel Pipe Scaffold on Full Place to Build An Engineering of a Concrete Access Bridge on a Reservoir's Spillway
下载PDF
导出
摘要 溢洪道交通桥全长21 m,净高8.815 m,宽度6.5 m,净跨度20 m;由桥面板、四根主梁与八根次梁相结合为整体现浇钢筋混凝土梁板结构,混凝土总方量76 m3。为满足下部交通条件,加快施工进度,充分利用现有材料,采用钢桁架和满堂红扣件式钢管脚手架联合支撑结构。文中介绍支承方案选择,支撑结构的布置,荷载分析及应用。 The total length of an access bridge in a certain reservoir's spillway is 21 m. The bridge's net height is 8.815 m. Its width is 6.5 m. Its net span is 20 m. It is a reinforced concrete slab-beam structure casted in place, and is composed by bridge surface slab, four primary beams and eight secondary beams. Its total quantity of concrete is 76 m3. In order to ensure the traffic demand under the bridge, for quickening construction schedule and to sufficiently use present existing material, a formworks-supporting structure is adopted which is composed by a steel truss support structure and a fastener steel pipe scaffold on full place. In the paper, the selection of the support scheme, the layout of support structure, the analysis of loads and its application are introduced.
作者 张俊峰
出处 《山西水利科技》 2014年第3期55-57,共3页 Shanxi Hydrotechnics
关键词 钢桁架 钢管脚手架 支撑结构 荷载分析 steel truss steel pipe scaffold supporl structure load analysis
  • 相关文献

同被引文献6

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部