供应中断风险下供应链恢复能力投资决策及协调 被引量:3

Supply Chain Recovery Capacity Investment Decision and Coordination under Supply Disruption
下载PDF
导出
摘要 为了减缓供应商生产运营中断对制造商带来的供应中断风险,制造商需要在突发事件前优化供应链恢复能力投资水平。引入CVaR来刻画供应链在突发事件下的应急目标,建立了一定置信水平控制下的供应链恢复能力投资的决策模型,进而揭示了制造商风险规避程度对供应链最优恢复能力投资水平的影响。分权供应链下,制造商运用基于绩效的契约来激励供应商投资合适的恢复能力,以协调供应链。结论表明,CVaR可以恰当描述供应链恢复的能力投资行为,当风险规避程度越高,供应链最优恢复能力投资越多;当单位中断时间的惩罚系数的条件期望值等于单位中断时间的商誉成本的条件期望值时,供应链进入协调状态。 To mitigate the risk of supply disruption to the manufacturers resulting from the supplier's pro-duction interruption , the manufacturer needs to optimize the level of supply chain recovery capacity invest-ment prior to a disruption .Conditional Value-at-Risk ( CVaR ) is introduced to characterize the supply chain's operation goal under disruption .A decision-making model of supply chain recovery capacity invest-ment under certain confidence control level is established .Furthermore , the degree of the manufacture's risk aversion on the optimal level of supply chain recovery capacity investment is investigated .In a decen-tralized supply chain , the manufacturer uses the Performance-Based Contract to encourage suppliers to in-vest right recovery capacity in order to coordinate a supply chain .The results show that the CVaR criteria can describe the behavior of supply chain recovery capacity investment , the higher the degree of the manufacture's risk aversion , the more the optimal supply chain recovery capacity is .The supply chain is coordinated when the conditional expected value of penalty coefficient of unit outage time is equal to the conditional expected value of goodwill cost of unit outage time .
出处 《工业工程》 北大核心 2014年第3期27-32,共6页 Industrial Engineering Journal
基金 国家自然科学基金资助项目(70732003 71171070) 国家社科基金青年项目(10CGL026) 浙江省自然科学基金资助项目(LY12G02009 LQ12G01004)
关键词 供应中断 能力恢复 应急管理 供应链协调 条件风险值(CVaR) supply disruption capacity recovery disruption management supply chain coordination conditional value-at-risk (CVaR)
  • 相关文献

参考文献14

  • 1Banker S. Volcano disrupts European supply chains. [ EB/ OL]. (2010-00-22). http://logistiesviewpoints, com/2010/ 04/22/volcano-disrupts -european -supply -chains.
  • 2朱传波,季建华,陈祥国.突发性需求下的供应链能力决策及应急协调机制[J].计算机集成制造系统,2011,17(5):1071-1077. 被引量:8
  • 3Kaplan S, Garrick B J. On the quantitative definition of risk [ J]. Risk Analysis, 1981,1 ( 1 ) : 11-27.
  • 4Bakshi N, Kleindorfer P. Co-opetition and investment for supply-chain Resilience [ J ]. Production and Operations management, 2009,18 (6) :583- 603.
  • 5Wang Y M, Gilland W, Tomlin B. Mitigating supply risk: dual sourcing or process improvement.7 [ J]. Manufacturing and Service Operations Management, 2010, 12 ( 3 ) : 489- 510.
  • 6Liu S, So K C, Zhang F. The effect of supply reliability in a retail setting with joint marketing and inventory decision [ J ]. Manufacturing and Service Operations Management, 2010, 12(1) :19-32.
  • 7朱传波,季建华.考虑供应商风险的订货与可靠性改善策略研究[J].管理评论,2013,25(6):170-176. 被引量:12
  • 8Kim S H, Tomlin B. Guilt by association: strategic failure prevention and recovery capacity investments [ J ]. Manage- ment Science,2013, 59(7) : 1631-1649.
  • 9Iyer A V, Deshpande V, Wu Z. Contingency management under asymmetric information [ J ]. Operations Research Let- ters, 2005,33(6) :572-580.
  • 10Kim S H, Cohen M, Netessine S, et al. Contracting for in- frequent restoration and recovery of mission-critical systems [J]. Management Science, 2010, 56(9) :1551-1567.

二级参考文献66

共引文献48

同被引文献38

引证文献3

二级引证文献42

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部