摘要
三道渠铁路专用线位于内蒙古自治区准格尔旗境内,专用线拟接轨于巴准线三道渠(预留)车站。根据储煤工艺园区的规划,以能够充分利用既有铺架基地设施,减少工程投资、满足运输作业需要为原则,结合地形、地貌等外部环境,对南侧纵列牵出式方案及南侧横列牵出式方案进行比较分析,推荐南侧纵列牵出式方案,为三道渠集运站煤炭提供外运保障。
Sandaoqu special railway line is located in the Inner Mongolia Autonomous Region Zhungeer.The special line is planned to the Sandaoqu (reserved)station.According to the planning of the coal storage technology park,in order to be able to make full use of both laying base facilities,reduce the project investment,meet the transportation needs,combined with the terrain,topography and other external environment,the paper makes a comparative analysis on the column pull type scheme and the transverse pull type scheme.And South tandem pull-out type scheme is recommended to provides transportation security for coal transportation of Sandaoqu station.
出处
《铁道建筑技术》
2014年第8期65-67,共3页
Railway Construction Technology
关键词
巴准线
三道渠站
牵出式
方案比选
Bazhun railway Sandaoqu station draw-out scheme comparison