燃气轮机动力涡轮热负荷机械运转试验方法

Thermal-Load Mechanic Running Test of Power Turbine
下载PDF
导出
摘要 阐述了利用工厂动力设备,在非专用试验车台上,进行兆瓦级大功率工业燃气轮机动力涡轮工厂检验性试车的方法。采用空气管路连接动力涡轮进气口与排气口,构成密闭闭环回路,利用电动机驱动动力涡轮运转,涡轮叶片搅动空气使其升温,实现了热态空负荷机械运转的试验状态,达到了在额定工作转速下进行机械磨合运转试验,和在一定温度下对动力涡轮进行热态检验试验的目的。本方法对其他型号动力涡轮试车具有重要参考价值。 A rig test method was illustrated for the power turbine of the high-power industrial gas turbine of MWs order on unspecialized test rig using plant power facility. An air line was used to connect the power turbine inlet with its outlet to construct a closed circuit loop, using electric motor to drive the power turbine, with the turbine blades stirring air to heat the air. In this way, a closed circuit cycle was constructed through air-line connection and the power turbine was driven by electric motor. The power turbine was given me-chanic grounding-in test at normal operation speed and thermal test verification by heating air , making a mechanic running test of thermal state and void load. The study is of great importance of reference for the test of other types of power turbines.
出处 《燃气涡轮试验与研究》 北大核心 2014年第4期48-50,21,共4页 Gas Turbine Experiment and Research
关键词 工业燃气轮机 动力涡轮 机械运转 热态试车 空负荷试验 industrial gas turbine power turbine mechanic running thermal state test void load test
  • 相关文献

参考文献5

  • 1化学工业部.HG/T3650-1999烟气轮机技术条件[S].2000.
  • 2API Std 616-1998,用于石油、化工、燃气工业的燃气轮机[S].
  • 3某型燃驱压缩机组动力涡轮转子临界转速计算报告[R].四川成都:中国燃气涡轮研究院,2012.
  • 4吴爱中.动力涡轮在外力拖动下的工况分析[J].汽轮机技术,2004,46(5):359-362. 被引量:2
  • 5某首台燃气轮机动力涡轮拖转试验大纲[R].西安:西安航空动力股份有限公司,2013.

共引文献6

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部