摘要
简要介绍了某电厂原室外蒸汽管网系统及换热站工艺流程,通过对原室外蒸汽管网及换热站运行过程中存在问题的分析,提出了正确安装波纹补偿器,合理布置疏水器,加强设备运行管理等改造措施,使企业获得了较好的经济效益。
This paper briefly introduced the process of a power plant outdoor steam pipe network system and heat exchange station, through the analysis on existing problems in outdoor steam pipe network and heat exchange station running process, put forward correctly installation of corrugated compensator, reasonably setting steam trap, strengthen of equipment operation management and other transformation measures, made the business enterprise acquired better economic benefits.
出处
《山西建筑》
2014年第29期148-149,共2页
Shanxi Architecture
关键词
蒸汽管网
换热站
疏水器
检查井
改造
steam pipe network, heat exchange station, steam trap, inspection well, transformation