期刊文献+

基于蒙特卡洛仿真的项目完工成本概率预测 被引量:8

A Forecasting Method for Project Cost Probability at Completion Based on Monte Carlo Simulation
下载PDF
导出
摘要 在项目完工成本概率预测问题的研究中,传统挣值分析法中对项目完工成本的预测没有考虑到项目成本的不确定性,预测结果均为单一值。为解决上述问题,根据挣值分析法原理和项目各活动成本分布的特征,结合项目实施过程中的活动成本与进度绩效信息,给出活动完工成本的三点估计,即最乐观值、最可能值和最悲观值,并提出基于蒙特卡洛仿真的项目完工成本概率预测方法。上述方法综合考虑了项目成本的不确性,给出了预测结果的区间范围和概率分布。案例分析表明改进方法的预测结果符合项目成本的随机性特征,且预测精确度较高。 In traditional earned value analysis method, forecasting for project cost at completion does not consider the project cost uncertainty and the predictive results are too simple. According to the theory of earned analysis meth- od and the cost distribution characteristics of activities in project, three point estimates of activity cost at completion, namely the most optimistic value, the most likely value and the most pessimistic value, were given based on activity cost and schedule performance during project execution. Based on these, a forecasting method for project cost proba- bility at completion based on Monte Carlo simulation was put forward. The method comprehensively considers project cost uncertainty and gives the interval area and probability distribution of predictive value. The case analysis shows that the prediction results of this method conform to the random characteristics of project cost and the prediction accuracy is higher.
出处 《计算机仿真》 CSCD 北大核心 2014年第9期301-304,309,共5页 Computer Simulation
基金 江苏省高校哲学社会科学基金项目(2013SJB6300075) 教育部人文社科规划基金项目(10YJA630082)
关键词 项目完工成本概率预测 蒙特卡洛仿真 挣值分析法 活动成本绩效 活动进度绩效 Forecasting for project cost probability at completion Monte Carlo simulation Earned value analysis method Activity cost performance Activity schedule performance
  • 相关文献

参考文献11

二级参考文献38

  • 1周晓宏.项目管理中的挣值管理方法研究——兼与戚安邦同志商榷[J].数量经济技术经济研究,2005,22(4):143-148. 被引量:25
  • 2丁宝峰,张宏国.挣得值分析在项目进度评测中的改进方法[J].信息技术,2006,30(2):14-16. 被引量:18
  • 3赵峰.基于关键路径的挣值分析法的优化研究[J].工业技术经济,2007,26(6):59-63. 被引量:22
  • 4Christensen D S. The costs and benefits of the Earned Value management process [ J ]. Acquisition Review Quarterly, 1998, Fall: 79-85.
  • 5Abba W Y. Earned Value management--reconciling government and commercial practices: for people involved in Earned Value[J]. Project Management, 1997, Special Issue :43-50.
  • 6Fleming Q W. Cost/Schedule Control Systems Criteria:the management guide to C/SCSC[M]. Chicago: Probus Publishing Co., 1992.75-87.
  • 7Project Management Institute. A Guide to Project Management Body of Knowledge[M]. PMI, 2000.87-95.
  • 8Cass D J. Earned Value program for DOE projects[A].AACE-I TRansactions-1998[C]. AACE-I, 1998. 187-194.
  • 9AKINTOYE A S, MACLEOD M J. Risk analysis and management in construction [J]. Intern J Proj Manag,1997, 15(1): 31-38.
  • 10AL-BAHAR. Systematic risk management approach for construction project [J]. J Const Engin - Manag,1990, 116(4): 533-546.

共引文献87

同被引文献81

引证文献8

二级引证文献28

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部