摘要
沱江一桥复线桥北引桥为双幅分离式连续梁,周边环境和地形条件复杂。利用桥位处原沱江一桥及房建工程的建筑结构,因势利导,降低施工影响,方便进行现浇施工。
The north approach bridge of Tuojiang first bridge with complex line is double separate continuous beam, which has complex peripheral environment and terrain conditions. By using the original Tuojiang bridge and the construction structu-re of housing project, and the favorable terrain to reduce the construction effect, and carries on the cast-in-situ construction conveniently.
出处
《城市建筑》
2014年第4期291-291,297,共2页
Urbanism and Architecture
关键词
复杂地形
引道工程
现浇施工
交通及人行组织应急预案
complex terrain
approach road engineering
cast-in-situ construction
traffic and pedestrian organization
emerg-ency plan