摘要
在列车不断提速的背景下,铁路工程施工质量要求也在不断提高。T型梁作为铁路的重要组成部分,使用传统施工方法,稳定性和刚度都不理想。为满足铁路干线提速的要求,文章对铁路 T 型梁横向预应力联接施工技术进行了探讨。
Under the background of the acceleration of the train, the railway engineering construction quality is also imp-roving. The stability and stiffness of T beam are not ideal, as an important part of railway, by using the traditional constr-uction method. In order to meet the requirements of railway speed increasing, the construction technology of T beam Tran-sverse prestress connection in the railway is discussed in this article.
出处
《城市建筑》
2014年第11期320-320,351,共2页
Urbanism and Architecture
关键词
铁路T型梁
预应力张拉
管道压浆
T beam in railway
the prestressed tensioning
pipe grouting