颍河倒虹吸施工期基础变形特征分析 被引量:1

Analysis on deformation characteristics of Yinghe inverted siphon foundation in construction period
下载PDF
导出
摘要 颍河倒虹吸是南水北调中线禹州和长葛段最大的河渠交叉建筑物,为了解倒虹吸工程施工期基础及管身的变形情况,对施工全过程进行了安全监测,并对建筑物基础监测成果进行了分析。分析认为:由于建筑物上部自重逐渐增加,底板下沉量也随之加大;底板界面应力大小与建筑物箱体自重、回填物荷载以及水压力荷载等相关;基础渗透压力主要受外水压力作用较为明显。 Yinhe inverted siphon works is the largest river-canal crossing structure in Yuzhou-Changge section of Middle Route Project of South-to-North Water Diversion. In order to master the deformation condition of foundation and pipe body of inverted siphon, the monitoring was conducted in the whole construction period. The analysis shows that the settlement of bottom plate interface increases with the gradual increase in self-weight of upper structure, the stress of bottom plate has relation with the box weight of structure, backfilling load and water pressure etc. , the seepage pressure is obviously influenced by water pres-sure.
作者 李申亭
出处 《人民长江》 北大核心 2014年第17期85-88,共4页 Yangtze River
关键词 变形特性 垂直位移 界面压力 渗透压力 倒虹吸 deformation characteristics vertical displacement interface pressure seepage pressure
  • 相关文献

参考文献2

二级参考文献1

  • 1SL 303-2004,水利水电工程施工组织设计规范[S].

共引文献2

同被引文献4

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部