500kV变电站隔离开关分合闸不到位抢弧故障分析 被引量:9

Analysis on Arcing Fault of Divide-shut Brake Lacking of Isolation Switch in 500kV Substation
下载PDF
导出
摘要 为了解决500 kV变电站隔离开关分合闸不到位抢弧故障的问题,结合阳江500 kV变电站隔离开关操作时所出现的故障问题,介绍了该故障的基本情况,并对故障原因进行了初步分析,认为开关操作所产生的暂态电磁干扰是导致隔离开关分合闸不到位的原因。在此基础上,从理论上对故障的机理进行分析,并对变电站二次侧暂态过电压进行现场测量,得出电磁干扰主要是通过高频电流互感器耦合到二次回路;再根据故障机理分析和现场测量提出利用在二次回路加装电涌保护器来解决该类问题。 In order to solve problem of arcing fault of divide-shut brake lacking of isolation switch in 500 kV substation,this paper introduces basic information of this fault by combining fault of isolation switch operation in Yangjiang 500 kV substa-tion and analyzes reason for the fault which is considered to be transient electromagnetic interference produced in switch op-eration. On the basis of analysis,fault mechanism was analyzed from angle of theory. Field measuring on transient overvolt-age at secondary side of the substation was conducted and conclusion was that electromagnetic interference was coupled sec-ondary circuit via high frequency current transformer. According to fault mechanism analysis and field measuring,method for solving this kind of problem was proposed which was to install surge protection device in secondary circuit.
出处 《广东电力》 2014年第8期64-69,共6页 Guangdong Electric Power
关键词 隔离开关 分合闸 电磁干扰 拉弧 开关操作 isolation switch divide-shut brake electromagnetic interference arcing switch operation
  • 相关文献

参考文献12

二级参考文献59

  • 1贾江波,张乔根,李彦明.低压系统串级浪涌抑制配合的研究[J].电瓷避雷器,2004(3):43-46. 被引量:22
  • 2赵志斌,崔翔,张波,李琳.应用矩量法计算变电站内的空间电磁场[J].中国电机工程学报,2004,24(11):148-153. 被引量:24
  • 3齐磊,崔翔,卢铁兵,谷雪松.屏蔽电缆的分布参数测量及瞬态分析[J].中国电机工程学报,2005,25(6):119-123. 被引量:28
  • 4Wiggins C M, Thomas D E, Nickel F S. Transient electromagnetic interference in substation[J]. IEEE Transactions on Power Delivery, 1994, 9(5):1869-1883.
  • 5Jakel B W Muller A B. Transients in medium voltage switchgear: ts, models and coupling[C]//Proceedings of the International Conference on Electromagnetic Interference and Compatibili ty. New Delhi, India: [s.n.], 1999: 69-74.
  • 6Lu Binxian, Wang Zezhong, Li Chengrong, et al. The switching transient electric field measurements in a 500 kV substation[C]//3rd International Symposium on Electromagnetic Compatibility. Beijing, China: Peoples Posts & Telecommunications Publishing House, 2002: 194-197.
  • 7Yu Gang, Jinhang He, Mao Bicheng, et al. Electromagnetic interference in control cables of substation caused by short circuit fault[C] //Proceedings 2002 International Conference on Power System Technology. Kunming, China: Yunnan Science & Technology Press, 2002, 2 : 980-984.
  • 8Carsimamovic S, Bajramovic Z, Ljevak M, et al. Very fast electromagnetic transients in air insulated substations and gas insulated subtations due to disconnector switching[C]//International Symposium on Electromagnetic Compatibility. Chicago, USA:[s. n. ], 2005,2: 382-387.
  • 9Pretorius p H, Britten A C, Van Coller J M, et al. Evaluation of the coupling mechanisms of electromagnetic disturbances resulting from disconnector switching in substations: experimental design and initial results[C] // Proceedings of the 1998 South African Symposium on Communications and Signal Processing. Rondebosch, South Africa: The Institute of Electrical and Electronic Engineers, Inc, 1998: 315-318.
  • 10Tae-Seung Song, Won-Seo Cho, Cheol-Soo Goo. Measurement and analysis of EMI at main control room in Uljin nuclear power plant [C]//3rd International Symposium on Electromagnetic Compatibility. Beijing, China: Peoples Posts & Telecommunications Publishing House, 2002~ 374-377.

共引文献79

同被引文献42

引证文献9

二级引证文献17

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部