新疆中天山山区玉溪莫勒盖隧道偏压坍方处治技术分析研究(英文) 被引量:1

Study on treatment technology of bias tunnel collapse in the mountain area of Tianshan in Xinjiang
下载PDF
导出
摘要 以G217乔尔玛至那拉提公路玉溪莫勒盖隧道为依托,针对隧道出口段K723+911~K723+919坍方,从衬砌受力及变形、地形、水文地质条件方面分析得出围岩偏压是该坍方主要原因,通过模型试验及现场测量,研究偏压坍方处治技术,分析总结各工况下隧道偏压坍方病害特点及规律,提出处治措施建议。模型试验及现场监控结果表明:采用CRD法施工、扩大注浆范围、增设注浆小导管锁脚、加强支护参数等方法对坍方处治后,拱顶下沉变形速率为0.4~1.5 mm/d,周边收敛变形速率为0.5~2.2 mm/d,受力最不利的右拱腰处压力及应变月度增大幅度分别为3.97%和2.35%,说明处治较好地控制了坍方体变形和受力。 We analyze the collapses of K 723+911~K723+919 in the exit section of Yu-xi-mo-le-gai Tunnel, which connects G217 Qiao-er-ma and Na-la-ti Road.Based on Lining stress and deformation , project topography and hydrogeological conditions , we found that the non-uniform rock pressure is the main reason of these collapses .The model experiments and field surveys proposed the methods to well a-void the collapse , which include CRD method construction , expanding grouting range , additional grou-ting small catheter locking pin and strengthening support parameters .After adopting these methods , the vault subsidence deformation rate is 0.4~1.5 mm/d, and the convergence deformation rate of the sur-roundings is 0.5~2.2 mm/d.Furthermore , the force most unfavorable pressure at the right arch waist and strain monthly increase by 3.97%and 2.35%, respectively .These methods can significantly control the deformation and force of the collapse .
出处 《黑龙江大学工程学报》 2014年第3期138-146,共9页 Journal of Engineering of Heilongjiang University
基金 Innovation group project of National Natural Science Fund(40821001)
关键词 玉溪莫勒盖隧道 模型试验 偏压坍方 处治技术 Yu-xi-mo-le-gai tunnel model experiment bias tunnel collapse treatment technology
  • 相关文献

参考文献4

二级参考文献18

共引文献129

同被引文献6

引证文献1

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部