摘要
某区位于滨海填海地区的隧道,在盾构到达端头存在富水砾砂层、前期加固效果较差情况下,首次利用了盾构到达克泥效辅助接收技术,顺利完成了盾构接收。该技术的成功应用为富水砂层盾构接收提供了选择,并为类似工程提供了工程经验。
The tunnel locates in the coastal reclamation areas, and the author first uses the shield to the clay shock method auxiliary receiving technology and successful y completes the shield arrival in the poorer situation of the arrival of shield rich water sand gravel layer and the early stage of the reinforce-ement effect. The successful application of this technology pr-ovides a choice for rich water mud shield, and provides the en-gineering experience for similar projects.
出处
《城市建筑》
2014年第17期394-395,共2页
Urbanism and Architecture
关键词
富水砾砂层
克泥效
rich water sand gravel layer
clay shock method