一种面向区域目标的敏捷成像卫星单轨调度方法 被引量:16

An Improved Single-orbit Scheduling Method for Agile Imaging Satellite Towards Area Target
原文传递
导出
摘要 针对传统卫星调度方法难以满足应急观测强时效性的问题,提出一种针对敏捷成像卫星的调度方法。首先动态计算敏捷卫星观测摆角、幅宽和持续时间,再以平行条带分割区域目标,获得最小姿态调整时间;在此基础上,设计等步长搜索算法求解对区域目标的最佳观测点。构建了包含4颗敏捷成像卫星的STK仿真场景,仿真结果说明该方法在提高观测目标覆盖率的同时减少了获取影像的时间。 Traditional satellite scheduling method has difficulties to meet the need for timely response in emergency observation missions. In this paper, an improved single-orbit scheduling method is proposed for agile imaging satellites as a tentative solution. This method first dynamically calculates the observation angle, swath, and duration of the agile imaging satellite. Cutting of area targets are then performed using parallel strip, followed by the acquisition of minimum attitude transition time. A specialized step-size search algorithm is employed to find the best observation point towards the area target. In our experiments, the STK simulation scenario is constructed with four agile imaging satellites. The simulation results show that the new method improves the coverage of area target while reduces the image acquisition time.
出处 《武汉大学学报(信息科学版)》 EI CSCD 北大核心 2014年第8期901-905,922,共6页 Geomatics and Information Science of Wuhan University
基金 国防预研基金资助项目(GFZX0404010502)~~
关键词 敏捷成像卫星 区域目标 单轨调度 动态分解 STK agile imaging satellite single-orbit scheduling area target dynamic decomposition STK
  • 相关文献

参考文献6

二级参考文献34

  • 1阮启明,谭跃进,李菊芳,陈英武.对地观测卫星的区域目标分割与优选问题研究[J].测绘科学,2006,31(1):98-100. 被引量:15
  • 2徐雪仁,宫鹏,黄学智,金勇.资源卫星(可见光)遥感数据获取任务调度优化算法研究[J].遥感学报,2007,11(1):109-114. 被引量:29
  • 3王均.成像卫星综合任务调度模型与优化方法研究[D].国防科技大学,2007.
  • 4Walton J. Models for the management of satellite-based sensors[D]. Massachusetts Institute of Technology, 1993.
  • 5Claire R, Carmine P. Improving satellite surveillance through optimal assignment of assets (DSTO-TR-1488)[R]. Australian Government Department of Defence, 2004.
  • 6Goddard Space Flight Center. Landsat-D Worldwide Reference System (WRS) Users Guide[M]. 1981.
  • 7Greg J. Spot grid reference system (GRS)[J]. Geocarto International, 1986, 1(3): 55 -57.
  • 8Lemaitre M, Verfaillie G, Jouhaud F, et al. Selecting and scheduling observations of agile satellites[J]. Aerospace Science and Technology, 2002, 6(2): 367~381.
  • 9Mancel C, Lopez P. Complex optimization problems in space systems[C]// Proceedings of 13th International Conference on Automated Planning and Scheduling (ICAPS' 03). Trento, Italic: AAAI Press, 2003.
  • 10Potter W.A Photo Album of Earth:Scheduling Landsat 7 Mission Daily Activities[C].SpaceOPS,Tokyo,Japan,1998

共引文献77

同被引文献208

引证文献16

二级引证文献79

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部