为完成某港沉箱出运任务,根据预制场码头轨距、标高等参数对船舶进行相应改造。在船舶不上坞的情况下,这使得船舶性能和质量满足使用要求,缩短了改造工期,节约了改造成本,圆满完成沉箱出运任务。
In order to complete a port sit shipped caisson task, according to the plecast yard pier gauge, elevation and other parameters, the ship is traanformed. In the case offloating dock not on the dock; under the above measures, the foating dock can meet the performance and quality requirements, shorten the transformation period, save the cost of renovation, then, the task of caisson ship is successfully completed.
出处
《机电设备》
2014年第5期53-55,共3页
Mechanical and Electrical Equipment
关键词
船舶改造
坐底出运沉箱操作流程
坐底出运沉箱关键参数计算
ship traansformation
sit shipped caisson operating procedures
sit shipped caisson key parameter calculation