摘要 基于推导的泄槽底板抗滑稳定安全系数计算式,运用正交设计的直观分析法进行底板稳定性敏感性分析,结果表明阻滑板长度、底板长度和溢流平均速度是影响底板稳定的重要因素.从底板的抗滑稳定角度,分析及计算底板最大允许流速范围为15.33~40.67m/s.最后以实际工程为例,分析了泄槽底板在单一阻滑板加固作用下的抗滑稳定性以及阻滑板与底板的应力. On the basis of the derived calculation formula for the anti-sliding safety coefficient of chute bottom slab,the sensitivity analysis of bottom slab stability was performed using the intuitive analysis method with orthogonal design,which indicated that the lengths of anti-sliding plate and bottom slab,and the overflow average velocity are the main factors to affect the stability.From the perspective of anti-sliding stability,the maximum allowable flow velocity of the bottom slab was about 15.33~ 40.67 m/s.Based on one practical project,the anti-sliding stability of chute bottom slab and the stress between the anti-sliding plate and bottom slab were investigated under the reinforcement effect of single anti-sliding plate.
出处 《南水北调与水利科技》 CAS CSCD 北大核心 2014年第6期116-119,139,共5页 South-to-North Water Transfers and Water Science & Technology
基金 贵州省自然科学基金(黔科合J字[2010]2247) 贵州大学研究生创新基金(研理工2013048)
关键词 溢流面板堆石坝 泄槽底板 稳定分析 结构应力分析 overflow concrete faced rock-fill dam chute bottom slab stability analysis structural stress analysis
  • 相关文献

参考文献15

二级参考文献23

共引文献402

同被引文献26

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部