摘要
介绍了外墙外保温系统的构成,对外墙外保温系统中基层与胶粘剂的粘结强度进行了现场拉拔,分析了现场拉拔的要求及测点的选取方法,并对影响测值的各种因素作了研究,为实现检测数值的准确性奠定了基础。
The paper introduces the components of the external wall exterior thermal insulation system,undertakes the site pull-out test of the foundation layer and the bounding strength of adhesive of the external wall exterior thermal insulation system,analyzes the requirements and se-lected methods of the tested sites,and researches all of factors affecting the measured value,so as to lay the foundation for the accuracy of the tested number.
出处
《山西建筑》
2014年第31期208-209,共2页
Shanxi Architecture
关键词
外墙外保温系统
拉拔
因素
强度
external wall exterior thermal insulation system
pull-out
factor
strength