期刊文献+

压水堆核电厂超压分析探讨 被引量:5

Discussion on the Overpressure Analysis of PWR NPP
下载PDF
导出
摘要 本文介绍了核电厂一回路冷却剂系统、主蒸汽系统及安全壳系统的超压事故分析,涉及内容包括超压验收准则、初始参数和边界条件、分析范围、分析方法等。结合核电厂执照申请文件和最新研究成果,围绕核电行业要求"利益和安全平衡"的特殊原则,本文概述了在审评过程中遇到的问题及其解决方案,旨在探讨如何进一步完善超压分析,推进核电厂的执照申请和审评工作。 The article describes the main point about overpressure accident analysis of the primary coolant system, the main steam system, containment system of nuclear power plant, involving the acceptance criteria, the initial boundary conditions and parameters, analysis scope, methodology and so on. It combines with the power plant license files request and the latest research results, the specific principles of the requirements on the balance between interests and security around the nuclear power industry, outlining problems and solutions encountered in the review process. The aim is to explore how to further improve the overpressure analysis, promoting the power plant license requesting and review process.
出处 《核安全》 2014年第3期50-55,共6页 Nuclear Safety
关键词 核电厂 超压 事故分析 nuclear power plant overpressure accident analysis
  • 相关文献

参考文献8

二级参考文献45

共引文献54

同被引文献35

  • 1沈如刚.大亚湾核电厂全厂失电的后果及应急措施[J].核动力工程,1995,16(1):23-29. 被引量:4
  • 2陈艳华.广东核电站ATWS事故分析研究[J].核科学与工程,1995,15(1):1-8. 被引量:1
  • 3大亚湾核电运营管理有限责任公司.岭澳核电厂3号机组RCP-二回路环路流量超过机械设计流量准则的运行事件报告[R].深圳:大亚湾核电运营管理有限责任公司,2011.
  • 4福建宁德核电有限公司.福建宁德核电厂1号机组RCP环路流量及堆芯总流量超过机械设计流量准则的运行事件报告[R].宁德:福建宁德核电有限公司,2013.
  • 5辽宁红沿河核电有限公司.辽宁红沿河核电厂1号机组RCP环路流量及堆芯总流量超过机械设计流量准则的运行事件报告[R].大连:辽宁红沿河核电有限公司,2013.
  • 6国家核安全局.核电厂营运单位报告制度HAF 001/02/01-1995[S].北京:国家核安全局,1995.
  • 7福建宁德核电有限公司.宁德核电厂一期工程最终安全分析报告(FSAR)[R].宁德:福建宁德核电有限公司,2011.
  • 8DNMC.GNPS 1&2-Thermal hydraulic design report(PGX11300012FP1045GN Rev.C)[R].Shenzhen:DNMC,1991.
  • 9FRAMATOME.STEAM GENRATOR TUBE BUNDLEAND PART LIST RIGHT AND LEFT HAND SG(NEEG-F DB2212,Rev B,79/19TE)[R].Paris:FRAMATOME.
  • 10国家核安全局.HAF003核电厂质量保证安全规定[S].北京:国家核安全局,1991.