摘要
本文通过对10kV直埋敷设电缆遭外力破坏的故障实例,及运行工况的分析,结合运行中发现的薄弱点,提出防止直埋敷设电缆遭外力破坏导致事故的,运行、检修和新建施工的改进措施。
Directly buried installation based on 10 kV cable fault example of external force damage, and the analysis of the operation, combined with the weak spot, found in the operation of directly buried installation is put forward to prevent cable force damage cause of the accident, operation, maintenance and the improvement measures of new construction.
出处
《河南电力》
2014年第3期1-3,26,共4页
Henan Electric Power
关键词
供电可靠性
10KV电缆
直埋敷设
外力破坏
改进措施
power supply reliability
10 kV cable
Directly buried installation
External force damage
Improvement measures