冻结法在江底取水隧道修复工程中的应用 被引量:6

Application of Ground Freezing Method to Repair Project of River Bottom Water Taking Tunnel
下载PDF
导出
摘要 常熟发电厂江底盾构取水隧道施工中,发生突水涌砂事故后,采用填充冻结法来形成临时冻结封堵墙;然后排出隧道内积水,构筑永久封堵墙,为隧道工程下一步施工的安全、顺利进行提供了保障。实践表明,采用填充冻结法施工临时封堵墙,与隧道内灌注水下混凝土方法施工临时封堵墙相比,在复杂地质条件下,能有效防止突水涌砂事故发生,对隧道本体损伤较小,对相邻建筑物影响较小,且人员无需进入积水隧道内施工,可控性、安全性较高,具有推广应用价值。 During a construction of a river bottom shield water taking tunnel for Changshu Power Generation Plant, a backfill ground freezing method was applied to form a temporary freezing sealing wall after a water inrush and sand burst accident occurred. Then the standing water in the tunnel was drained and a permanent sealing wall was build to provide a protection to the following safety and successful construction of the tunnel project. The practices showed that in comparison with the application of a concrete pouring in water method in the tunnel to build a temporary sealing wall, under the complicated geological condition, the application of the backfill ground freezing method to build the temporary sealing wall could effectively prevent a water inrush and sand burst accident occurred, would have a less damage to the tunnel structure, a less influence to the neighboring buildings and would have no person required to work in the tunnel with standing water. Thus the backfill ground freezing method could have a high control and high safety with a promotion and application value.
出处 《建井技术》 2014年第4期12-16,共5页 Mine Construction Technology
关键词 冻结法 江底隧道 盾构 临时封堵墙 修复 ground freezing method river bottom tunnel shield temporary sealing wall repair
  • 相关文献

参考文献4

二级参考文献16

共引文献25

同被引文献108

引证文献6

二级引证文献43

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部