摘要
以晋江市某深基坑支护为背景,通过在工程现场实际调研及施工过程中遇到的可变或不可变因素,进而对原有支护设计进行优化补充,确保基坑稳定及工程人员、周边环境的安全。现场监测表明,该优化方案切实可行,可供类似工程的优化加固设计提供一些参考。
This paper, taking a deep foundation pit supporting in Jinjiang city as the background, through in the eugineering field encountered in the process of the actual research and the construction of mutable or immutable factors, and then optimize the original supporting design, guarantee the stability of toundation pit and engineering staff, the safety of the surrounding environment. Field monitoring show that the optimized scheme is feasible, and provide some references for the optimization of the reinforcement design for similar project.
出处
《福建建筑》
2014年第10期86-90,98,共6页
Fujian Architecture & Construction
关键词
深基坑
方案优化
施工控制
监测
Deep foundation pit
Scheme optimization
Construction control
Monitoring