结合杭州地铁四号线盾构工程的特点及设计要求,确定了该工程监测的内容,介绍了基准点和监测点的埋设位置,并对地表监测的方法步骤进行了论述,同时分析了监测结果,保证了盾构施工的安全进行。
Combining with the features of the shield project at the No. 4 Line of Hangzhou subway and its design requirements,the paper identifies the contents of the engineering supervision,introduces the burial location of datum point,indicates the methods and steps for the surface monitoring,and analyzes the monitoring result,so as to ensure the safety of the shield construction.
出处
《山西建筑》
2014年第32期209-210,共2页
Shanxi Architecture
关键词
地表沉降
监测
盾构
基准点
surface subsidence
monitoring
shield
datum point