摘要
广蓄电厂设计研究的备用变压器能够解决不同厂家不同型号变压器高低压侧连接相间距不同及高度不同、变压器底座设计不同等技术难点,并且还能解决一变两厂(站)备用的难题。该项目的实施,大大缩短了广蓄A、B两厂主变压器故障后的恢复时间,提高了系统运行的可靠性,节省了制造成本,科学的设计还大大降低了备变安装时的施工难度、及缩短了备变安装时的施工工期。
The design and research of standby main transformer in Guangzhou Pumped Storage Power Station need solve the technical problems of the connectors in high- and low-voltage sides with different spacing and heights and the different foundation of transformer to provide the reservation to the main transformers manufactured by two manufacturers respectively. The new standby main transformer can greatly reduce the recovery time of main transformer faults in the Plant A and B of Guangzhou Pumped Storage Power Station, improve the reliability of system operation, save manufacturing costs and reduce installation difficulty and time of transformer.
出处
《水力发电》
北大核心
2014年第11期1-3,100,共4页
Water Power
关键词
备用变压器
接口
自换位
设计
广州蓄能水电厂
standby transformer, connecting
self transposition
design
Guangzhou Pumped Storage Power Station